Sub topic 11
Counting and Scheduling Business Days
Assume you can enter formulas, use relative and absolute cell references, and apply date formats from the Format menu. This chapter uses a holiday list on a separate sheet named Holidays.
Business-day functions ignore regular days off, such as Saturday and Sunday. They can also ignore specific holidays. This is useful for service deadlines, payroll, project plans, and support tickets.
Counting weekdays with NETWORKDAYS
NETWORKDAYS counts working days between two dates. The count includes both the start date and the end date when they are working days.
=NETWORKDAYS(A2, B2, Holidays!A2:A20)If A2 is 2026-11-23 and B2 is 2026-11-30, the result excludes Saturday, Sunday, and every date listed in Holidays!A2:A20.
| Formula | Purpose |
|---|---|
| `=NETWORKDAYS(A2, B2)` | Count Monday-through-Friday days |
| `=NETWORKDAYS(A2, B2, Holidays!A2:A20)` | Also exclude listed holidays |
| `=NETWORKDAYS.INTL(A2, B2, 7, Holidays!A2:A20)` | Use a custom weekend number |
The NETWORKDAYS.INTL variant lets you define weekends other than Saturday and Sunday. Its third argument can be a weekend number or a seven-character pattern. The pattern uses Monday through Sunday order. A 1 means a nonworking day, and a 0 means a working day.
=NETWORKDAYS.INTL(A2, B2, "0000011", Holidays!A2:A20)This pattern treats Saturday and Sunday as the weekend.
Scheduling a due date with WORKDAY
WORKDAY returns the date reached after a number of working days. It skips weekends and optional holidays.
=WORKDAY(A2, 10, Holidays!A2:A20)This returns the date 10 working days after the date in A2. The starting date itself is not counted as day 1. If A2 is a Monday, the following Tuesday is normally the result for one working day later.
Use WORKDAY.INTL when your weekend differs from Saturday and Sunday:
=WORKDAY.INTL(A2, 10, "0000110", Holidays!A2:A20)Here, Friday and Saturday are nonworking days. The pattern has one position for each day from Monday through Sunday.
Prepare and check the holiday range
Each holiday should be a real date value, not text that only looks like a date. Build holiday values with DATE when necessary:
=DATE(2026, 12, 25)Keep the holiday range fixed when copying formulas:
=WORKDAY(A2, 10, Holidays!$A$2:$A$20)A holiday outside the start and end dates has no effect. Duplicate holidays also do not subtract twice.
Common errors include counting the wrong endpoint, using a text holiday, and choosing the wrong custom-weekend pattern. Format the result as a date so a serial number displays clearly.
Exercise
Exercise
A project starts on Monday, 2026-11-23. The holiday list contains Thursday, 2026-11-26. Which formula returns the date 5 working days later while excluding that holiday?
Show answer
=WORKDAY(DATE(2026,11,23), 5, Holidays!A2:A20)