Agreeing a Mutual Action Plan and Next Steps
A mutual action plan (MAP) is a shared document that lists the steps from today to a signed decision and, ideally, to the start of use. Each step has an owner and a date, and both the buyer and the seller sign up to it. This chapter covers how to build one, how to keep it alive, and what goes wrong.
Prerequisites
This chapter assumes you have read the earlier chapters on discovery, quantifying impact, qualification, the business case, objection handling, and multi-threading. You should be comfortable with the B2B sales cycle (lead, opportunity, close) and know what a CRM records. The MAP pulls those earlier pieces together into one schedule.
Why a MAP exists
Most stalled deals do not die from a "no". They fade because nobody owns the next step. A seller who ends a call with "I'll follow up next week" holds all the momentum. The buyer has no commitment, and any competing priority can push the deal aside.
A MAP changes three things:
- It makes the buyer's process visible. Legal review, security questionnaires, procurement, and budget approval often take longer than the evaluation itself. You learn about them early instead of at the last minute.
- It moves ownership to both sides. Buyer tasks sit next to seller tasks, so the buyer is a participant and not an audience.
- It tests real intent. A buyer who will not name dates or introduce a stakeholder is telling you something about the deal's health.
A MAP is not a closing trick. It works only when it reflects the buyer's real internal process and the buyer's own goal, such as a launch date or a contract renewal deadline.
Work backward from the buyer's date
Start with the event that matters to the buyer, not the date you want to close. Ask questions like:
- "What needs to be true by then for this to count as a success?"
- "Is there a date, such as a renewal, a budget cycle, or a launch, that this project has to meet?"
- "What happens if this slips by a quarter?"
The answers connect back to the problem and impact you quantified in discovery. If the cost of the problem is high and a deadline exists, the buyer has a reason to protect the timeline. If you cannot find a compelling event, the plan will have soft dates, and you should treat the deal as less likely to close.
Then list the steps backward from that date. A typical sequence looks like this:
- Confirm the goal and success criteria with the economic buyer.
- Run a technical evaluation or pilot.
- Complete security and compliance review.
- Present the business case to the decision group.
- Complete legal and procurement review.
- Sign the contract.
- Kick off implementation.
Working backward exposes impossible dates. If legal review usually takes three weeks and the buyer wants to sign in two, you can raise that now.
What goes into a MAP
A useful MAP is short. One page or one shared spreadsheet is enough. Each row should carry these fields:
| Field | Purpose | Example |
|---|---|---|
| Step | The concrete action | Security questionnaire completed |
| Owner (buyer side) | The named person who acts | Priya, IT security lead |
| Owner (seller side) | The person who supports | Sam, solutions engineer |
| Due date | A calendar date, not "soon" | 12 March |
| Status | Not started, in progress, done, blocked | In progress |
| Dependency | What must happen first | Needs NDA signed |
| Notes | Risks or decisions | Priya needs the SOC 2 report |
Name people, not departments. "Legal will review" has no owner. "Marcus in legal reviews the contract by 19 March" does.
Include both your tasks and theirs. If the plan lists only buyer tasks, it reads as a demand. If it lists only seller tasks, the buyer has made no commitment.
Link steps to the stakeholders
The MAP is where multi-threading becomes concrete. For each step, check which stakeholder it involves. If the economic buyer appears nowhere until the signature step, you have a risk: the person who approves the budget has not seen the business case. Add a step that puts the case in front of them early.
A worked example
A company sells workforce scheduling software. In discovery, the operations director said overtime costs her about 400,000 per year, and she wants the problem fixed before the busy season starts on 1 October. The seller proposes this MAP, built backward from 1 October.
| Date | Step | Buyer owner | Seller owner |
|---|---|---|---|
| 5 Aug | Agree success criteria and pilot scope | Operations director | Account executive |
| 12 Aug | Share staffing data export for the pilot | Operations analyst | Solutions engineer |
| 26 Aug | Pilot results review | Operations director, two shift managers | Solutions engineer |
| 2 Sep | Security questionnaire returned | IT security lead | Solutions engineer |
| 9 Sep | Business case reviewed with finance | Finance director | Account executive |
| 16 Sep | Contract draft to legal | Legal counsel | Account executive |
| 23 Sep | Signature | Operations director | Account executive |
| 1 Oct | Go-live for first site | Operations director | Customer success manager |
The seller did not invent these dates. At each step, the seller asked, "Who else needs to see this, and how long does that usually take?" The finance review on 9 September exists because the operations director said finance would want to check the 400,000 figure.
Presenting the plan
How you introduce the plan matters more than the document. Offer it as help, and ask for corrections:
- "Based on what you told me, here is how I'd expect this to run. What am I missing?"
- "Who else usually weighs in on a purchase like this?"
- "What has slowed down similar projects here before?"
Build it with your main contact in a live conversation, then share it in a format both sides can edit. Common choices are a shared spreadsheet, a shared document, or a page in a deal-room tool. A PDF attached to an email is hard to keep current.
Ask for explicit agreement: "Does this timeline work for you? Are you comfortable owning steps 2 and 3?" A silent nod is weak. A reply that names changes shows real engagement.
Running the plan after it is agreed
A MAP loses value if nobody opens it again. Use these habits:
- Review it at every meeting. Start each call with the plan and confirm what changed.
- Update dates openly. If a step slips, ask what caused it and whether later dates are still realistic.
- Treat blocked steps as information. A missed buyer task can signal low priority, a missing stakeholder, or an unraised objection. Ask about it directly and without blame.
- Keep the CRM in sync. Record the next step, its date, and the close date from the plan, so forecasts reflect the buyer's timeline.
- Always end a call with a dated next step. "Let's talk soon" is not a next step. "Thursday at 2pm, Priya and I will review the questionnaire" is.
Common failure modes
| Problem | Why it happens | What to do |
|---|---|---|
| Buyer ignores the plan | It was built by the seller alone | Rebuild it with the buyer and tie it to their goal |
| Dates are all "end of month" | No real process knowledge | Ask for the last time this kind of purchase was made, and map that path |
| Only one contact is involved | Single-threaded deal | Add steps that require other stakeholders to attend or approve |
| Plan stops at signature | Seller focuses on closing | Add kickoff and first-value steps, which also feed account growth |
| Buyer goes silent mid-plan | Priority changed or champion lost influence | Contact other stakeholders and revisit the business reason |
| Plan is too detailed | Thirty rows nobody reads | Keep to the major milestones and group small tasks |
A MAP also has limits. In small, fast deals with one decision maker, a full plan is overhead, and a clear next step is enough. In large deals with procurement-driven processes, the buyer may have a fixed internal timeline, and your job is to fit into it and not to reshape it.
Connecting the MAP to the rest of the process
The MAP uses the outputs of earlier work. The business case supplies the reason for the deadline. Qualification tells you who the economic buyer is and what the decision process looks like. Multi-threading provides the people to assign. Objection handling supplies the risks to schedule around, such as a security concern that needs a dedicated review step. After signature, the same plan extends into onboarding and the first value milestone, which is where account growth begins.
Summary of practices
- Anchor the plan to a date the buyer cares about.
- Build it with the buyer, not for them.
- Use named owners, calendar dates, and dependencies.
- Include steps for other stakeholders, especially the economic buyer.
- Review it in every meeting and use slips as signals.
- Extend it past signature to kickoff.
Exercise
A seller has a MAP with these rows: "Security review: IT, end of month" and "Legal review: legal, soon". The only buyer contact is the project manager. Name three problems with the plan and one fix for each.
Show answer
First, the owners are departments, not people, so nobody is accountable. Fix: ask who in IT and legal will do the work and write their names. Second, the dates are vague ("end of month", "soon"). Fix: agree calendar dates and ask how long these reviews took on the last purchase. Third, there is only one contact, so the deal is single-threaded and the economic buyer is absent. Fix: add a step where the economic buyer reviews the business case before the contract stage.
Exercise
Your buyer says the project must be live by 1 October. Legal review usually takes three weeks and the security questionnaire takes two. Outline how you would work backward and what you would raise with the buyer.
Show answer
Start at 1 October as go-live, then place signature a few days before to allow for setup. Put legal review three weeks before signature and start security review in parallel, because it is two weeks long and does not depend on legal. Raise with the buyer that the contract draft must reach legal by roughly early September, and that the pilot and business case review must finish before that. If the buyer's current dates do not leave this time, say so now and ask whether the go-live date can move or whether reviews can start earlier.