Sub topic 11
Performing an Existing Duty as Consideration
This chapter assumes that you understand offer and acceptance, the difference between a promise and a gift, and how common law courts use precedent. The issue here is whether doing something you already owe someone can support a new promise.
The traditional pre-existing duty rule
Consideration must be something given in exchange for a promise. A person normally gives no new consideration by promising to do what that person already has a legal duty to do.
The rule applies most clearly when the duty is owed to the promisor under an existing contract.
Example:
- A builder agrees to construct a house for £100,000.
- During the work, the builder demands another £10,000.
- The owner promises to pay it if the builder completes the original work.
- The builder completes the work but gives nothing additional.
The builder has performed an existing contractual duty. Under the traditional rule, that performance is not consideration for the extra £10,000. The owner’s promise is therefore generally unenforceable unless another doctrine applies.
The same principle can apply when a public or legal duty is performed. A police officer cannot usually demand a separate payment for doing ordinary police work, because that work is already required by public duty.
Important qualifications
The rule is not absolute.
A person may provide consideration by performing more than the existing duty. In Hartley v Ponsonby, sailors who stayed on a ship after many crew members had deserted were treated as doing more than their original duty. Their promise to continue working could support extra pay.
A contractual duty owed to a third party can also be consideration for a new promise. In Scotson v Pegg, delivery of goods under an existing contract was capable of supporting a promise made by another party. The key point is that the claimant was not already contractually bound to the person making the new promise.
Practical benefit and contract variations
The modern qualification concerns practical benefit. In Williams v Roffey Bros, a contractor promised extra payment to a subcontractor who was already bound to complete the work. The court held that the subcontractor’s continued performance could be consideration because the contractor gained practical benefits, including avoiding delay and the cost of finding a replacement.
This approach does not make every promise to pay more enforceable. The additional promise must usually be made freely, the promisor must receive a practical benefit, and the variation must not result from economic duress. Economic duress is unlawful pressure that leaves the other party with no realistic choice.
A method for analysing facts
Ask these questions:
- What new promise is said to be enforceable?
- What act or promise is offered as consideration?
- Was that act already required by a contract or public duty?
- Was the duty owed to the same promisor or to someone else?
- Was anything additional done?
- Did the promisor receive a practical benefit?
- Was the new promise obtained through economic duress?
Exercise
A contractor is already bound to finish a project. The client promises an extra £5,000 if the contractor finishes on time. The contractor agrees, and the client avoids a costly delay. Is the contractor’s performance automatically consideration for the extra payment?
Show answer
No. Performance of the existing duty is traditionally insufficient. However, under the practical-benefit approach, the client’s avoided delay may support consideration if the variation was freely made and was not obtained through economic duress.