Sub topic 13
Writing lessons people can act on
This chapter assumes you have run or joined a retrospective and found a root cause for at least one problem. It covers the next step: turning that finding into a written lesson that a future team can read and act on. You should be comfortable with the terms scope, deliverable, sponsor, and root cause.
Why most lessons go unused
Many lessons learned registers are full of entries like these:
- "Communication needs to improve."
- "Requirements were unclear."
- "Better planning is required."
These entries record that something went wrong. They don't say what to do differently, who should do it, or when it applies. A reader on the next project can agree with them and still change nothing.
An actionable lesson is one a stranger can read without context and answer three questions about:
- What happened, and why?
- What should be done differently?
- Who is responsible for making that change?
The parts of a good lesson
A well-formed lesson has a small set of fields. Each field has a job.
| Field | Purpose | Common mistake |
|---|---|---|
| Category | Lets readers filter by area, such as requirements or procurement | Inventing a new category for every entry |
| What happened | States the observable event, with facts and numbers | Describing feelings or blaming a person |
| Root cause | Names the underlying reason, not the symptom | Repeating the symptom in other words |
| Recommendation | Gives a concrete action for next time | Writing a vague wish ("improve testing") |
| Applies to | Says which kinds of project should use it | Leaving it blank, so readers can't tell if it's relevant |
| Owner | Names a role who will carry the change forward | Naming nobody, or "the team" |
| Status | Shows whether the lesson was adopted | Never updating it after the first entry |
Here is a complete example in the format a register might use:
- id: LL-007
category: Requirements
what_happened: Acceptance criteria for the reporting module were agreed late, so two sprints of work were reworked.
root_cause: Criteria were drafted by the project team without review from the business users who would sign off.
recommendation: Have the business owner review and approve acceptance criteria before development starts on each deliverable.
applies_to: Projects with a business sign-off step
owner: PMO lead
status: Adopted into project kickoff templateLook at what this entry does well. The event is specific: one module, two sprints. The root cause is a process gap, not a person. The recommendation is a step someone can put into a checklist. The status shows the lesson already changed a template.
From weak to strong: a worked rewrite
Start with a weak entry:
> Testing was done too late.
This tells the reader nothing about what to do. Rewrite it in steps.
- Add facts to "what happened". Instead of "too late", say what the delay cost. For example: "User acceptance testing began two weeks before go-live. It found 14 defects, and 5 of them needed design changes."
- Ask why until you reach a cause you can change. Why did testing start late? Because the test environment was not ready. Why? Because nobody had been assigned to build it. The cause is that environment setup was never a task in the plan.
- Turn the cause into an action. "Add test environment setup to the work breakdown structure, with a named owner and a finish date before testing begins."
- Set the scope. This applies to any project that has user acceptance testing.
- Assign an owner. A role works better than a person's name, because people move on. Use "Test manager" or "PMO lead".
The result is a lesson a planner can apply in ten minutes.
Tests for quality
Before you accept a lesson, check it against these questions.
- Specific. Does it name the event, the deliverable, or the step involved?
- Cause-based. Does the recommendation address the root cause, or only the symptom?
- Doable. Could someone start on the recommendation next week?
- Scoped. Does the reader know which projects it applies to?
- Owned. Is there a role responsible for it?
- Neutral. Does it describe the process rather than blame a person?
A lesson that fails two or more of these needs another pass.
Successes are lessons too
Teams often record only problems. Successes are worth the same treatment. A practice that worked is a lesson, but the team may not know why it worked. Apply the same method: describe what happened, find the cause of the success, and write it as a repeatable action.
For example, a team might find that a weekly 15-minute risk review with the supplier caught a delivery delay early. The lesson is not "the supplier relationship was good". It is "hold a weekly risk review with suppliers of long-lead items", applied to projects with external suppliers, owned by the procurement lead.
Common errors
- Recommending the impossible. "Never change scope" is not an action. State what to do when scope changes, such as "route every change request through the change board within five working days".
- Writing for yourself. You know what "the Phoenix issue" means. A future reader doesn't. Spell out names, systems, and acronyms.
- Bundling several lessons into one. If a lesson has two causes and two actions, split it so each can be adopted or rejected on its own.
- Skipping the owner. An ownerless lesson is rarely adopted. The owner decides whether it goes into a template, a training course, or a standard.
- Mixing facts and opinions. Keep "what happened" factual. Put interpretation in the root cause field, where it can be challenged.
- Over-generalizing. A lesson from a three-person internal project may not apply to a regulated, multi-vendor programme. The "applies to" field prevents misuse.
Handing the lesson to the register
A lesson is only finished when it can be found and acted on. After writing it, check that it has a unique ID and a category so it can be searched later. Also confirm that its owner has agreed to the recommendation, and set a status such as "Proposed", "Adopted", or "Rejected, with reason". The next chapter covers how the register keeps these entries current.
Check your understanding
Exercise
A retrospective produced this entry: "The vendor was late and caused delays. Need better vendor management." Rewrite it as an actionable lesson. Assume you found that the vendor's delivery dates were never tied to payment milestones, the delay was three weeks, and it affected the integration phase. List the fields you would fill in.
Show answer
A strong answer includes these fields. What happened: the vendor delivered the interface module three weeks late, which delayed the integration phase by three weeks. Root cause: the contract did not link payment milestones to delivery dates, so the vendor had no financial reason to meet them. Recommendation: for contracts with delivery dependencies, tie each payment milestone to an accepted delivery date and include a review of delivery progress every two weeks. Applies to: projects with external vendors on the critical path. Owner: procurement lead (a role, not a person). Status: proposed. The answer must not blame the vendor or an individual, and must contain an action someone could put into a contract template.
Exercise
Name two tests you would apply to decide whether a lesson is ready to enter the register, and explain what failing each one looks like.
Show answer
Any two of these are correct. Specific: a failing lesson says things like "communication was poor" with no event, deliverable, or step named. Cause-based: a failing lesson recommends a fix for the symptom (for example "test earlier") without addressing why the problem happened. Doable: a failing lesson recommends something nobody could start next week (for example "never change scope"). Scoped: a failing lesson leaves readers unable to tell which projects it applies to. Owned: a failing lesson names no role, or only "the team". Neutral: a failing lesson names a person as the cause.