Sub topic 6
Deadlines and tasks that block other people or work
This chapter assumes you already keep a single task list and know the difference between important and urgent work. It also assumes you can read your calendar to see how much time you really have. Here you learn to read two signals that often decide whether a task belongs in today's three: the deadline attached to it, and who or what is waiting on it.
Why deadlines and dependencies need their own check
Importance and goal alignment tell you what is worth doing. They do not tell you when it must happen. A task can be worth doing and still be safe to leave until next week. Another task can be minor, but if you skip it today, three people cannot start their work.
Two facts are worth checking for every candidate:
- Deadline: the date or time after which the task loses value or causes a problem.
- Dependency: a link between tasks or people. If task B cannot start until task A is finished, B depends on A. A task that holds up others is a blocker.
These facts feed directly into the selection step. If you ignore them, you tend to pick tasks by how they feel, and the cost shows up later as a missed date or a stalled colleague.
Reading a deadline properly
A date on a task is not the whole story. Ask these questions about each one.
Is the deadline real?
Deadlines come in two kinds:
- Hard deadlines have an external consequence if missed. Examples are a tax filing, a client delivery, a release freeze, or a booking that closes.
- Soft deadlines are targets you or someone else chose. Missing them has little external cost. Examples are "I'd like to finish this by Friday" or "send me something when you can."
Treat hard deadlines as constraints. Treat soft deadlines as information. If a soft deadline keeps appearing on your list, either confirm it with the person who set it or remove it.
How much lead time does the task need?
The deadline is the last moment the work can be done. The date you must start is earlier. Work backward:
- Estimate the working time the task needs.
- Add waiting time for reviews, approvals, or other people's replies.
- Add a buffer, because estimates are usually optimistic.
- Subtract the total from the deadline. The result is the latest start date.
A report due Friday that needs four hours of writing and a day for review has a latest start date of Wednesday or earlier. On Wednesday it is not yet urgent by the calendar, but it is already a candidate for today's three if Wednesday's other work is lighter.
What happens at the deadline?
Some tasks fail completely when late, such as a registration that closes. Others degrade gradually, such as a report that is a day late. Tasks that fail completely deserve earlier attention than tasks that degrade.
Tasks that block other people or work
A blocking task is often small. It might be a reply, an approval, a review, or a decision. Its cost is not the effort it takes you. Its cost is the waiting it creates for others.
Compare two tasks:
| Task | Effort for you | Who waits if you skip it today |
|---|---|---|
| Approve a colleague's expense report | 5 minutes | One person, who cannot submit their claim |
| Review a teammate's pull request | 30 minutes | A teammate, and possibly the release |
| Reorganize your notes | 2 hours | Nobody |
The first two have a small cost to you and a visible cost to others. The third has the opposite shape. When you weigh these, count the waiting time as part of the consequence of skipping.
Two directions of dependency
Dependencies run in two directions, and you need to check both.
- Tasks that others wait on. You are the blocker. Doing the task today frees someone else.
- Tasks you wait on. Someone else is your blocker. You cannot finish your own task until their input arrives.
For the second direction, the right move is often not to work on the blocked task at all. It is to send the request that unblocks you. That request is itself a candidate task, and it is usually quick.
In this chain, "Approve the design" is small, but three streams of work wait on it. If it is your task, it deserves a slot early in the day. A delay there spreads to everything after it.
Turning deadlines and blockers into a score you can compare
You do not need a formula, but a quick rating helps you compare tasks consistently. For each candidate, mark two things.
- Time pressure: none, this week, or today or tomorrow.
- Blocking effect: nobody waits, one person waits, or several people or a release wait.
A task with high time pressure and a wide blocking effect almost always makes the cut. A task with neither can wait unless it aligns strongly with a goal. Mixed cases need judgment, which is where the other criteria from earlier chapters come in.
A worked example
Suppose your candidate list for Thursday looks like this:
- Draft the quarterly summary (due next Wednesday, 3 hours of work, needs a manager review before sending)
- Reply to the vendor about the contract change (vendor waits, contract signing is Friday)
- Review Priya's draft (Priya needs comments before her Friday meeting)
- Clean up old email folders (no deadline)
- Update the team wiki page (soft target, no one is waiting)
Apply the two ratings:
| Candidate | Time pressure | Blocking effect |
|---|---|---|
| Quarterly summary | This week (latest start is Monday given review time) | Nobody yet |
| Vendor reply | Today or tomorrow | One external party, plus a signing |
| Review Priya's draft | Today or tomorrow | One colleague |
| Clean up email | None | Nobody |
| Update wiki | None | Nobody |
The vendor reply and the review of Priya's draft are strong picks. Both are short, and both unblock someone with a near deadline. The quarterly summary is the third candidate, because its latest start date is close. The email cleanup and wiki update go on the "not today" list.
Using the code example's "Not today" list
The plan format from this tutorial records what you left out. This matters for deadlines. When you leave out a task with a deadline, write the deadline next to it so you can see when it will force its way back.
### Not today
- Quarterly summary (due Wed; start by Mon at the latest)
- Update team wiki (soft target, no one waiting)
- Clean up email folders (no deadline)Writing the latest start date next to a deferred task turns "I'll get to it" into a checkable commitment. Your daily review can then scan the list for dates that are getting close.
Edge cases
Everything is due today
If more than three tasks are due today, you have an overload problem, not a selection problem. Do these in order:
- Check whether each deadline is hard or soft. Some will drop out.
- Ask whether any can be delegated or renegotiated. A short message such as "I can deliver this tomorrow morning, is that acceptable?" often succeeds.
- Rank the rest by consequence of failure, then by blocking effect.
Do not extend the list to five. A longer list gives you more things to worry about without giving you more time.
The blocker is not you
If the blocking task belongs to someone else, you cannot complete it. Your task is to ask, remind, or escalate. Write it as an outcome with a definition of done, for example "Ask Dana for the final figures and get a delivery time (done = Dana confirms a time)."
The deadline is unknown
Some tasks have no stated date but still have a hidden one, such as a colleague who is "waiting for your thoughts." If you cannot tell, ask. A one-line message that says "When do you need this by?" is often the quickest way to decide whether the task belongs in today's three.
A blocking task is large
If a blocking task takes more than a few hours, do not leave it all or nothing. Identify the smallest piece that unblocks others, such as a rough outline or a partial answer, and make that the task. The spine's rule that a task can be "a clear part of it" applies here.
Common mistakes
- Treating every deadline as equal. Hard and soft deadlines need different treatment.
- Looking only at the due date. The latest start date is the one that tells you when to act.
- Overlooking small blockers. A five-minute reply can be worth more than a two-hour task.
- Letting blocked work sit silently. If you are waiting on someone, send the request today.
- Using blockers as a reason to take on everything. Blocking others is a factor to weigh, not an obligation to answer every request instantly.
Pulling it together
Add two checks to your selection checklist: "What happens if this slips by a day?" and "Who is waiting on me, or on whom am I waiting?" Answering them takes a minute per candidate. They keep your choices tied to real consequences instead of mood.
Exercise
Your candidates for today are: (a) send a 10-minute approval that three teammates need before they can start work, (b) write a 3-hour report due in two weeks, (c) update a slide deck due next Tuesday, which needs a day of review, and today is Monday, (d) ask a colleague for numbers you need for task (c). Which would you place in today's three, and why?
Show answer
Choose (a), (d), and (c). Task (a) is short and blocks three people. Task (d) unblocks you for (c), and a request costs little. Task (c) has a latest start date of about today or tomorrow because of review time and a buffer. Task (b) is far off and has no one waiting, so it goes on the "not today" list with its latest start date noted.
Exercise
What is the difference between a deadline and a latest start date, and how do you calculate the latter?
Show answer
The deadline is when the task must be done. The latest start date is the last day you can begin and still finish on time. Estimate the working time, add waiting time for reviews or replies, add a buffer, and subtract the total from the deadline.