Assume you know means, standard deviations, p-values, confidence intervals, and the purpose of the Analyze phase in DMAIC. This chapter focuses on what happens when one project asks several statistical questions.
Why multiple comparisons matter
A multiple comparison is a set of related statistical tests performed on the same project data. Each test usually uses a significance level, or alpha, of 0.05. Alpha is the accepted probability of a Type I error, which means rejecting a true null hypothesis.
One test at alpha = 0.05 has a 5% false-positive risk when its null hypothesis is true. The risk increases when you run many tests. For example, comparing four process groups creates six pairwise comparisons:
| Groups | Pairwise comparisons | Approximate chance of at least one false positive |
|---|---|---|
| 4 | 6 | 26.5% when all null hypotheses are true |
The approximate probability is:
1 - (1 - 0.05)^6 = 0.265This calculation assumes independent tests, so it is an approximation. The main lesson remains: a collection of tests needs a collection-level error strategy.
Control the error rate
The family-wise error rate is the probability of making at least one Type I error across a family of tests. Common ways to control it include:
- Bonferroni correction: divide alpha by the number of tests. With six tests and alpha = 0.05, use 0.05 / 6 = 0.0083 for each test. This method is simple but can be conservative.
- Holm correction: order the p-values and apply progressively less strict thresholds. It usually has more power than Bonferroni while controlling the same family-wise error rate.
- Tukey’s honestly significant difference test: a common choice for all pairwise comparisons after one-way ANOVA.
- Planned contrasts: define a small number of meaningful comparisons before collecting or analyzing the data. These are often more efficient than testing every possible pair.
ANOVA first tests the overall null hypothesis that all group means are equal. A significant ANOVA does not identify which groups differ. Use an appropriate adjusted post hoc method for that question.
Common pitfalls
Testing until something is significant
Running many analyses and reporting only the smallest p-value is a form of selective reporting. Changing the outcome, subgroup, or test method after seeing results can also create biased evidence. State the primary question, outcome, alpha, and comparison plan before examining the results when possible.
Treating p-values as effect sizes
A small p-value does not show that a difference matters to the customer or process. Report the estimated difference, confidence interval, and a practical threshold such as the maximum acceptable defect reduction or cycle-time change.
Ignoring dependence
Repeated measurements from the same unit are not independent observations. Treating them as independent can make the sample appear larger than it is. Use a paired test, repeated-measures method, or an appropriate model.
Forgetting the process context
Statistical significance can result from a large sample and a tiny difference. Before recommending a process change, compare the estimated effect with the project goal, measurement error, cost, and operational risk.
Exercise
Four groups produce six pairwise comparisons. If the project uses Bonferroni correction with alpha = 0.05, what p-value threshold should each comparison use?
Show answer
Each comparison should use 0.05 / 6 = 0.0083, approximately.