Sub topic 13
Changing scope and configuration after go-live
This chapter assumes you know how an implementation project, scope items, and configuration activities fit together in Central Business Configuration (CBC). It also assumes you know that CBC deploys configuration from a development system to test and production systems. Here you will see how to change a live solution without breaking it.
Why changes after go-live need a process
After go-live, the production system holds real business data. You cannot edit its configuration directly. All changes start in CBC, in the same project that built the solution, and move through the landscape in the same way as the original configuration.
There are two kinds of change:
- Scope change: you add or remove scope items, or change the enterprise structure and scoping answers that go with them.
- Configuration change: you adjust values inside scope items that are already active, using configuration activities, fine-tuning, or expert configuration.
The change flow
Changes are made in the development system, tested in a quality system, and then deployed to production. The sequence is the same for both kinds of change.
Changing scope
Scope changes carry more risk than value changes, because they can add processes, add configuration activities, and change what users see.
- Open the implementation project and go to the scope selection.
- Add the new scope item, or deselect one you no longer need.
- Review any new scoping questions the item brings. Answer them before you continue.
- Check the enterprise structure. A new scope item may need organizational units that do not exist yet.
- Complete the new configuration activities that appear.
- Deploy to the test system, then to production.
Adding a scope item is the common case and is usually safe. Removing one is more delicate. Check whether live data, open documents, or other scope items depend on it before you deselect it. If you are unsure, test the removal in a system that holds a copy of realistic data.
Changing configuration
For a value change, find the activity in the project and edit it. Use fine-tuning for the common adjustments. Use expert configuration only for cases the guided activities do not cover. Expert configuration gives you more freedom, so the risk of inconsistent settings is higher.
Keep these habits:
- Change one topic at a time, so a failed test points to one cause.
- Record why you made each change, so the next administrator can understand it.
- Test with the business processes that use the setting, not only with the setting itself.
Planning and timing
Plan changes around the business calendar. Avoid deploying during period-end closing or other busy periods. Agree on a window with the business owners, tell users about visible changes in advance, and keep a short list of what was deployed and when.
Also keep in mind that the test system must stay close to production. If the systems drift apart, a successful test says little about what will happen in production.
Common mistakes
| Mistake | Effect | Prevention |
|---|---|---|
| Deploying straight to production without testing | Faults reach live users | Always run the change through the test system first |
| Removing scope without checking dependencies | Broken processes or orphaned data | Review dependent scope items and live data first |
| Changing several things in one deployment | Hard to find the cause of a failure | Group changes by topic |
| Forgetting new scoping questions | Incomplete configuration | Review all new questions after each scope change |
Exercise
Your company wants to add a new scope item after go-live. List the steps from selecting the item to having it live in production.
Show answer
Add the scope item in the implementation project. Answer the new scoping questions. Check and extend the enterprise structure if needed. Complete the new configuration activities. Deploy to the test system and test the processes. When the test passes, deploy to the production system.
Exercise
Why should you check dependencies before deselecting a scope item in a live solution?
Show answer
Other scope items, open documents, or users may still rely on it. Removing it can break processes, and the business data it created does not necessarily disappear.