Changing scope and configuration after go-live
This chapter explains how to change a live SAP S/4HANA Cloud Public Edition solution through Central Business Configuration (CBC). It assumes you know what an implementation project, a scope item and a configuration activity are. It also assumes you know how configuration is deployed from the development system to the test and production systems. The chapter covers the two kinds of post-go-live change, the way CBC handles them, and the errors that cause the most trouble.
Why post-go-live change is different
Before go-live, you can reshape the solution freely. The production system is empty, so a wrong scope choice costs only rework. After go-live, the production system holds business data such as open sales orders, posted journal entries and active suppliers. A configuration change now has to work with that data.
Public Edition also limits direct access. You do not change production configuration in the system itself. You make the change in CBC and then deploy it through the landscape. This keeps the systems consistent and leaves a record of what changed.
Two kinds of change
Post-go-live changes fall into two groups.
- Scope changes add or remove scope items, or change the enterprise structure. An example is adding a scope item for a new business process, or adding a company code for a new legal entity.
- Configuration changes adjust how existing scope behaves. An example is changing a setting in a fine-tuning activity, or answering a scoping question differently.
Scope changes have wider effects. A new scope item can bring new configuration activities, new scoping questions and new business content. Configuration changes usually touch fewer objects.
| Aspect | Scope change | Configuration change |
|---|---|---|
| Typical trigger | New process, new country, new legal entity | Adjusted business rule or setting |
| Where you work in CBC | Project scope, enterprise structure, scoping questions | Configuration activities |
| Follow-up work | New activities, possibly new roles and master data | Usually limited to the affected activity |
| Risk to live data | Higher | Lower, but depends on the setting |
How CBC supports change
CBC does not let you edit the production system's configuration in place. Instead, it works with a project that lives in the landscape, and changes reach production only through deployment.
The usual path has these steps:
- Open the implementation project in CBC. After go-live, this is the same project you used for the initial setup.
- Make the scope or configuration change in the project.
- Complete the new or changed activities.
- Deploy the change to the test system.
- Test the change with business users.
- Deploy the change to the production system.
The deployment sequence matters. You do not skip the test system. The deployment to production takes the configuration that was validated in the earlier system.
Scope changes in detail
Adding a scope item
You add a scope item in the project's scope selection, using the Business Adaptation Catalog. The steps are the same as in the initial implementation, but the consequences differ.
- CBC may ask new scoping questions that did not apply before. Answer them before you continue.
- New configuration activities appear. Some are guided configuration and some are fine-tuning.
- Some scope items need master data or business users that do not exist yet. Plan for these outside CBC.
- Some scope items depend on other scope items. CBC reports missing dependencies, and you need to add them too.
Check each new scope item for its prerequisites and for any enterprise structure it requires. A scope item that needs a plant or a sales organization cannot work until that organizational unit exists.
Removing a scope item
Removal is more restricted than addition. If a scope item has already produced business data in production, taking it out of scope can leave that data without a supporting configuration. Treat removal as a decision that needs business sign-off, and check what CBC allows for the item in question. When in doubt, leave the item in scope and stop using it in the business.
Changing the enterprise structure
Adding to the enterprise structure, for example a new company code or plant, is a normal post-go-live task. Changing or deleting existing units is much harder, because transactional data refers to them. Plan the structure with growth in mind during the initial project, so later additions do not force you to rework existing units.
When you add a unit, CBC may ask you to finish the configuration activities that depend on it. Skipping these leaves the new unit unusable even though it exists.
Configuration changes in detail
Most configuration changes are made in fine-tuning activities. Their general behavior is the same as before go-live. The difference is that the setting now applies to live data, so you need to consider what existing documents and master records will do.
Questions to ask before you change a setting:
- Does the setting apply only to new documents, or does it also affect existing ones?
- Is the change reversible? If not, you need a test with realistic data first.
- Does another process rely on the old value?
Changing an answer to a scoping question can also change which activities apply. Review the activity list after you change an answer, and do not assume the list stays the same.
Expert configuration
Expert configuration covers special cases that guided configuration and fine-tuning do not handle. Because it reaches more deeply into the system, use it with the most care after go-live. Document why each expert change was needed, since the reason is hard to recover later.
Handling the landscape during a change
Your landscape usually has a development system, a test system and a production system. After go-live, the systems can drift apart if you are not careful, so several habits help.
- Deploy in order, and do not change configuration in a downstream system on its own.
- Avoid several parallel changes that touch the same objects. When two people edit the same area, the later deployment can overwrite the earlier one or cause conflicts.
- Keep the test system representative of production. Test results mean little if its data and configuration differ greatly from production.
- Check the deployment status and logs after each step. A deployment that finishes with errors still needs follow-up.
Releases and the software update cycle
SAP S/4HANA Cloud Public Edition receives updates on a regular cycle, and the Business Adaptation Catalog changes with it. New scope items appear, and existing ones may change. When you plan a post-go-live scope change, check that the scope item you want exists in your release and review what changed. Treat an update as a reason to look at your scope again, since new capabilities may replace things you built by hand.
Common errors
- Changing production first. Any configuration made outside the CBC path creates a mismatch with the project. Make every change in CBC and deploy it.
- Adding scope without scoping questions. If you add an item and ignore the new questions, activities may be missing or wrong.
- Skipping the test system. A change that works in development can still fail on real data in production.
- Ignoring dependencies. A scope item added without its prerequisites leaves processes that cannot run.
- Mixing unrelated changes in one deployment. If it fails, you cannot tell which change caused the problem. Group changes by purpose.
- No record of the reason. Months later, nobody knows why a setting differs from the standard. Keep a change log with the request and the approver.
A practical checklist
Before you deploy a post-go-live change, confirm the following.
- The change has an approved request and a named owner.
- You know whether it is a scope change or a configuration change.
- All new scoping questions are answered and all new activities are complete.
- The change was deployed to the test system and business users tested it.
- Dependent scope items, organizational units and master data are ready.
- You have a plan for what to do if production behaves differently than expected.
- The deployment window avoids peak business hours, such as period-end closing.
Exercise
Your company opens a new plant and wants to add a scope item for a process that needs that plant. List the order of steps you follow in CBC and say why you do not edit the production system directly.
Show answer
Open the existing implementation project, add the plant to the enterprise structure, add the scope item from the Business Adaptation Catalog, and answer any new scoping questions. Complete the new configuration activities, deploy to the test system, test with business users, and then deploy to production. You do not edit production directly because Public Edition keeps configuration consistent through CBC deployment. A direct edit would leave the project and the production system out of step and would bypass testing.
Exercise
A colleague wants to remove a scope item that was used for a year and has posted documents in production. What should you check before agreeing, and what is a safer option if the removal is risky?
Show answer
Check whether CBC allows the removal, what business data exists for the item, which other processes depend on it, and whether the business has signed off. Test the removal on realistic data in the test system first. A safer option is to keep the item in scope and stop using it in the business process.
Exercise
You change the answer to a scoping question after go-live. Why should you review the activity list afterward?
Show answer
A different answer can add or remove configuration activities. If you do not review the list, you may miss new activities that must be completed, and the deployed configuration may be incomplete.