Sub topic 6
Recording the Purchase: Journal Entries
This chapter assumes you know double-entry bookkeeping, can read a balance sheet and income statement, and understand present value basics. The earlier chapters decided which costs belong in an asset. This chapter shows how to record them.
The accounting goal
A purchase journal entry does three things:
- It puts every capitalisable cost into one asset account, so the carrying amount reflects the full cost of getting the asset ready for use.
- It sends costs that do not qualify, such as training, to expense.
- It credits the right account for how each cost is settled: cash, accounts payable, a loan, or a provision.
The entry usually has one debit to the asset and several credits. The entry is straightforward. Mistakes usually come from classifying the individual costs wrongly.
Worked example: a purchased machine
Use the numbers from the earlier cost build-up. A company buys a machine with these terms:
| Item | Amount | Treatment |
|---|---|---|
| List price | 500,000 | Capitalise |
| Trade discount | (25,000) | Reduces cost |
| Import duty (non-refundable) | 20,000 | Capitalise |
| Delivery | 8,000 | Capitalise |
| Installation | 12,000 | Capitalise |
| Testing | 5,000 | Capitalise |
| Staff training | 3,000 | Expense |
The cost to capitalise is 500,000 − 25,000 + 20,000 + 8,000 + 12,000 + 5,000 = 520,000. This code checks the arithmetic and builds the entry lines:
purchase_price = 500_000
trade_discount = 25_000
import_duty = 20_000
delivery = 8_000
installation = 12_000
testing = 5_000
training = 3_000
cost = purchase_price - trade_discount + import_duty + delivery + installation + testing
entry = [
("Dr", "Machinery", cost),
("Dr", "Training expense", training),
("Cr", "Accounts payable - supplier", purchase_price - trade_discount + delivery),
("Cr", "Customs authority payable", import_duty),
("Cr", "Accounts payable - installer", installation + testing),
("Cr", "Cash", training),
]
debits = sum(a for side, _, a in entry if side == "Dr")
credits = sum(a for side, _, a in entry if side == "Cr")
assert debits == credits, (debits, credits)
for side, account, amount in entry:
print(f"{side:2} {account:32} {amount:>9,}")The assertion confirms that debits equal credits (523,000 each). The assumption here is that the supplier invoices delivery together with the machine, the installer invoices installation and testing, and the training is paid in cash. In practice the payee for each cost depends on who invoices it.
The compound entry reads:
| Account | Debit | Credit |
|---|---|---|
| Machinery | 520,000 | |
| Training expense | 3,000 | |
| Accounts payable (supplier) | 483,000 | |
| Customs authority payable | 20,000 | |
| Accounts payable (installer) | 17,000 | |
| Cash | 3,000 |
The trade discount does not get its own line. It is netted against the price on the invoice, so the supplier is owed 475,000 for the machine plus 8,000 for delivery.
Recording costs as they arrive
Costs rarely arrive on one day. Delivery, installation and testing happen over weeks or months. Most entities do not wait for the final invoice. They record each cost against the asset as it is incurred.
For a large project, use a clearing account for assets not yet ready for use. Commonly it is called "Construction in progress" or "Assets under installation". Each invoice is debited to it. When the asset is ready for use, you transfer the total to the proper asset class and start depreciation.
cip = 0
invoices = [
("Machine, net of discount", 475_000),
("Import duty", 20_000),
("Delivery", 8_000),
("Installation", 12_000),
("Testing", 5_000),
]
for label, amount in invoices:
cip += amount
print(f"Dr Construction in progress {amount:>8,} ({label}) balance {cip:>8,}")
print(f"Transfer: Dr Machinery {cip:,} Cr Construction in progress {cip:,}")The two-step approach keeps a clean audit trail. It also stops depreciation from starting too early, because assets in the clearing account are not yet depreciated.
Other credit sides
The debit side is the same whatever the settlement method. The credit side changes.
- Cash purchase. Credit Cash or Bank.
- Purchase on credit. Credit Accounts payable. The asset is recognised when control passes, even if payment comes later.
- Bank loan. Credit Loan payable. If the lender pays the supplier directly, the cash never touches your account, but the entry is still Dr Asset, Cr Loan.
- Deposit and balance. Credit Prepayments or Advances for the deposit when paid. When the asset is delivered, debit the asset for the full cost, credit the prepayment for the deposit and credit Payable for the balance.
- Decommissioning obligation. Credit a provision for the present value of the restoration cost.
The decommissioning case shows a non-cash credit. If the company must restore the site after 10 years, expects to pay 100,000, and uses a 6% discount rate:
expected_cost = 100_000
rate = 0.06
years = 10
provision = expected_cost / (1 + rate) ** years
print(round(provision)) # 55839
# Dr Plant (asset cost) 55,839
# Cr Decommissioning provision 55,839No cash moves at purchase, yet the asset's cost rises by 55,839. Each year the provision is unwound, and the increase is recorded as a finance cost.
Recoverable taxes
A tax is capitalised only if it cannot be recovered. Import duty in the example is non-refundable, so it is part of cost. Recoverable sales tax or VAT is different. You record it as a receivable from the tax authority, not as part of the asset.
Suppose the supplier invoice is 100,000 plus 20% recoverable VAT:
| Account | Debit | Credit |
|---|---|---|
| Equipment | 100,000 | |
| VAT receivable | 20,000 | |
| Accounts payable | 120,000 |
If the VAT were not recoverable, for example because the entity makes exempt supplies, the full 120,000 would go to Equipment.
Common errors
- Capitalising training or general overhead. These are not directly attributable costs, so they go to expense.
- Using the gross price. The asset is recorded at the price net of the trade discount. Settlement discounts for early payment are treated separately and, under IAS 16, are generally also deducted from cost where they are reasonably certain.
- Forgetting the accrual. If installation is finished but not yet invoiced at the period end, accrue the cost. Otherwise the asset is understated and a liability is missed.
- Starting depreciation on the clearing account. Transfer to the asset class when the asset is ready for use, not when the last invoice is paid.
- Expensing a decommissioning obligation. If the obligation arises from installing the asset, it belongs in the asset's cost.
- Capitalising recoverable VAT. This overstates the asset and understates the receivable.
Documentation and posting controls
Each capitalised entry should be backed by the supplier invoice, a purchase order, and evidence that the asset was received and tested. Keep a fixed asset register with one line per asset: description, date ready for use, cost, class, and useful life. The register total must agree with the general ledger balance for each asset class. A monthly reconciliation catches costs posted to the wrong class or never transferred out of construction in progress.
Exercise
A company buys equipment with an invoice price of 200,000 plus 10% VAT that it can recover. It also pays 6,000 for transport, 4,000 for installation, and 2,500 to train operators. All amounts are on credit except training, which is paid in cash. Give the journal entry and state the cost of the equipment.
Show answer
The equipment cost is 200,000 + 6,000 + 4,000 = 210,000. VAT of 20,000 is recoverable, so it is a receivable, and training of 2,500 is an expense. Entry: Dr Equipment 210,000; Dr VAT receivable 20,000; Dr Training expense 2,500; Cr Accounts payable 230,000 (200,000 + 20,000 VAT + 6,000 + 4,000); Cr Cash 2,500. Debits and credits both total 232,500. (If transport and installation carry recoverable VAT too, that VAT would also go to the receivable.)
Exercise
A company must dismantle a facility in 5 years. The expected cost is 80,000 and the discount rate is 5%. The facility costs 400,000 to build and is paid in cash. Give the entry at the date the facility is ready for use.
Show answer
The provision is 80,000 / 1.05^5 = 62,682 (rounded). Entry: Dr Facility 462,682; Cr Cash 400,000; Cr Decommissioning provision 62,682.