Sub topic 2
Assigning Owners, Approvers, and Dates
Assume you already know common marketing channels, can use a spreadsheet or project tool, and understand how work moves from writers and designers to approvers. This chapter connects responsibility, status, and launch timing in one calendar.
Assigning owners and approvers
Every calendar item needs one person accountable for moving it forward. The owner coordinates the work, updates the entry, and raises blockers. An approver checks whether the item meets the required standard before publication. These roles can belong to different people.
| Field | Purpose | Example |
|---|---|---|
| Owner | Person responsible for progress | Priya |
| Approver | Person who gives final sign-off | Legal team |
| Channel | Place where the item ships | |
| Due date | Date the item must be ready | 2026-03-02 |
Assign an owner at the smallest useful level. A campaign can have a campaign owner, while each email, landing page, or social post has its own production owner. Record the approver when review is required. If approval depends on a function rather than a person, name the function and a backup contact.
Defining a status workflow
A status workflow is the fixed sequence an item follows. Use a small set of statuses with clear entry and exit rules:
planned: the item is accepted but work has not started.in_progress: the owner is producing or coordinating it.in_review: the approver is checking a defined version.changes_requested: the item needs updates before approval.approved: the item is ready to schedule or publish.live: the item has shipped.
The owner changes the status after each handoff. The approver should record the decision and any required changes in the item, rather than relying on private messages.
Planning backward from the launch date
Back-planning starts with the fixed launch date and subtracts the time needed for each step. This exposes late work before it reaches the final review.
from datetime import date, timedelta
lead_times = {"brief": 28, "draft": 21, "review": 10, "final_assets": 5}
launch = date(2026, 3, 16)
for step, days in lead_times.items():
print(step, launch - timedelta(days=days))Use calendar days only when that matches team practice. Otherwise, subtract working days and include holidays. Add buffer for external approvals or dependencies.
Exercise
An email launches on March 16. Review requires 10 days. What is the review due date?
Show answer
March 6, calculated as March 16 minus 10 calendar days.