Sub topic 7
Planning backward from the launch date
This chapter assumes you already have a calendar table with campaign, activity, owner and status fields, and a status workflow such as draft, in review and approved. Back-planning uses those pieces to turn one fixed date into a due date for every production step.
The idea
Back-planning starts with the date the audience sees the work. You subtract the time each step needs and work toward today. The result is a due date for each step. If the earliest due date has already passed, you know the launch is at risk before anyone starts working.
A lead time is the number of days a step must be finished before launch. Lead times differ by activity type. A social post may need a few days. A launch email with legal review may need a month.
Choosing lead times
Lead times come from your team's history, not from a template. For each step, ask how long it usually takes, including waiting time for feedback. Then add a buffer.
| Step | Typical work | Lead time (days before launch) |
|---|---|---|
| Brief | Goal, audience, message agreed | 28 |
| Draft | First copy and design | 21 |
| Review | Edits and approvals | 10 |
| Final assets | Files ready for scheduling | 5 |
Store these values in one place, such as a settings sheet, so the whole team plans with the same numbers.
Calculating due dates
The calculation is a subtraction. This script applies the lead times above to a launch date.
from datetime import date, timedelta
# Days before launch by which each step must be finished.
LEAD_TIMES = {"brief": 28, "draft": 21, "review": 10, "final_assets": 5}
def back_plan(launch: date) -> dict[str, date]:
return {step: launch - timedelta(days=days) for step, days in LEAD_TIMES.items()}
for step, due in back_plan(date(2026, 3, 16)).items():
print(step, due.isoformat())For a launch on 16 March 2026, the output is:
brief 2026-02-16
draft 2026-02-23
review 2026-03-06
final_assets 2026-03-11Each due date becomes a row in the calendar, linked to its parent activity and carrying the same campaign name.
Connecting the plan to status
A due date is only useful if you can compare it with progress. Each step should have a status from your workflow. Then you can ask a simple question each week: which steps are past their due date and not yet complete?
For example, if the draft was due on 23 February and the item is still marked draft on 25 February, the review window is already shrinking. Flag it, and decide whether to push the launch or shorten the review.
Common errors
- Counting calendar days when the team works business days. A 10-day lead time that spans two weekends gives only 6 working days. Decide whether your lead times are calendar or working days and say so in the settings sheet.
- Ignoring holidays and team absences. A computed date can land on a public holiday or when the owner is away. Check computed dates against a shared leave calendar.
- Forgetting approver availability. The review step depends on someone else's time. Confirm the approver's availability when you set the launch date.
- Using one lead-time set for everything. A paid ad and a webinar do not need the same steps. Keep a lead-time set per activity type.
- Not re-planning after a change. If the launch moves, recalculate every dependent date. Changing only the launch row leaves stale due dates behind.
Working with a tight timeline
Sometimes the launch date is fixed and the schedule does not fit. Compare the earliest computed due date with today. If it is in the past, you have three options: shorten a step, run two steps in parallel, or cut scope. Record the choice in the calendar so stakeholders see why a lead time differs from the standard.
Exercise
A launch email goes out on 20 April 2026. Using the lead times in this chapter, what is the due date for the review step, and what problem could arise if the review lead time is counted in calendar days?
Show answer
The review is due 10 days before launch, which is 10 April 2026. If the team works business days, the 10 calendar days include weekends and any public holidays, so reviewers may have fewer than 10 working days. The lead time should be defined as working days, or the date should be checked against a leave and holiday calendar.