Sub topic 1
Breach of Contract: Material and Minor Breaches
Prerequisites
This chapter assumes you know what makes a contract: an offer, an acceptance, and consideration (something of value exchanged). You should also understand the terms party, obligation, and performance. The focus is US common law. Rules vary by state, so this is general education, not legal advice.
Contract duties and what performance means
A contract creates duties. Each party must do what the agreement says. Performance is the act of carrying out those duties, such as delivering goods, paying money, or finishing work by a deadline.
What counts as a breach
A breach is a failure to perform a duty without a legal excuse. Any shortfall can be a breach, but the law also asks how serious it was. That seriousness decides what the other party may do next.
Promises, conditions, and why order of performance matters
A promise is a commitment to do something. A condition is an event that must happen before another duty becomes due. For example, a buyer's duty to pay may depend on the seller first delivering the goods. Order of performance matters because a party that skips a condition may not be able to demand the other side's performance.
Minor breach: the contract survives
A minor breach, also called a partial breach, is a failure that does not defeat the core of the bargain. The injured party must still perform its own duties and can sue for damages to cover its loss. The contract continues.
Material breach: going to the root of the bargain
A material breach, also called a total breach, goes to the heart of the deal. The injured party may stop performing and end the contract. Courts decide materiality case by case. The Restatement (Second) of Contracts section 241 lists the factors, which the next chapter covers.
Exercise
A contractor agrees to build a deck for $5,000 by June 1. The contractor finishes on June 3, and one board is a slightly different color. Is this a breach, and is it likely material?
Show answer
Yes, it is a breach because the deadline was missed and the work differs from the promise. It is probably minor. The deck is nearly complete, the delay is short, and the owner still gets nearly the full benefit of the bargain. The owner would likely have a claim for damages, such as the cost of fixing the color or the loss caused by the delay. The owner probably could not end the contract and refuse to pay.