Sub topic 1
Why Projects Need Explicit Responsibilities
Prerequisites
This chapter assumes you know basic project vocabulary: task, deliverable, stakeholder, and role. You should have worked on a project with at least two people. Reading a simple table is enough for the matrix section.
Why projects need explicit responsibilities
Most project delays come from unclear ownership, not from hard technical work. When nobody knows who signs off a deliverable, the task waits. When two people think they own it, the work is done twice or not at all.
A RACI matrix is a table that states who does what for each task. It gives every task a clear owner and tells everyone else how to take part. Before you build one, you need to know the four role codes.
Responsible, Accountable, Consulted, Informed
- Responsible (R): the person who does the work. A task can have several R people.
- Accountable (A): the one person who owns the outcome and approves the result. Each task has exactly one A.
- Consulted (C): people whose input is needed before the work or approval. This is a two-way exchange.
- Informed (I): people who must learn the outcome but do not give input.
A is not the same as R. A manager can be Accountable for a task that a developer is Responsible for. Mixing these up is the most common error in this model.
Reading the matrix: tasks, roles, and cells
Tasks are rows. Roles are columns. Each cell holds one code, or a combination such as A/R when one person both owns and does the work.
| Task | Product owner | Developer | Sponsor |
|---|---|---|---|
| Write requirements | A | R | I |
| Build feature | C | A/R | I |
| Approve release | R | C | A |
Read across a row to see every role's part in one task. Read down a column to see everything one role is involved in. An empty cell means that role has no part in the task.
Exercise
In the table above, which role is Accountable for "Approve release", and which role is Responsible?
Show answer
The Sponsor is Accountable. The Product owner is Responsible.