Sub topic 2
Time to market and the cost of delay
Prerequisites: This chapter assumes you know revenue, margin, and cash flow, can read a short Python script, and understand what a discount rate is.
Time to market and the cost of delay
Time to market is the time from starting work to the first customer using the capability. Building internally usually takes longer than buying. Each month of delay postpones revenue and gives competitors room. The cost of delay is the value lost by arriving late, and it can exceed the difference in build cost.
What it costs to buy: price, valuation, and premium
Valuation is your estimate of what a target company is worth on its own. The premium is the extra amount above that value you pay to gain control. Premiums vary widely across deals, so check comparable transactions in your sector. Total purchase cost also includes fees, integration spending, and any debt you assume.
Putting build and buy on the same footing with NPV
Net present value (NPV) is the sum of future cash flows, each discounted to today's value. Compare options with the same discount rate and the same time horizon.
def npv(cash_flows, rate):
return sum(cf / (1 + rate) ** year for year, cf in enumerate(cash_flows))
rate = 0.10
build = [-2, -2, -1, 0, 3, 3, 3] # $M per year
buy = [-10, -1, 3, 3, 3, 3, 3]
print(f"Build NPV: {npv(build, rate):.2f}")
print(f"Buy NPV: {npv(buy, rate):.2f}")Build comes out ahead here, at about 0.06 against about -0.57 ($M), because the buy option pays a large sum up front.
Adjusting for execution and integration risk
Costs are usually more certain than benefits. A build can overrun its budget, and a deal can miss its benefits. Keep costs at full value and multiply uncertain benefits by the probability they arrive.
Synergies: separating real value from wishful thinking
A synergy is value that exists only when two businesses combine, such as shared operations costs or cross-selling. Count a synergy only if you can name its mechanism, its size, the month it starts, and the person responsible. Subtract the cost of achieving it. If the premium exceeds the risk-adjusted synergy value, you pay the seller for work you have not yet done.
Exercise
Exercise
The buy option's benefits have a 70 percent chance of arriving. Using the same cash flows, what is the buy NPV, and is it still below the build NPV of about 0.06?
Show answer
The buy NPV is about -3.67 $M (the costs of -10.91 plus 0.7 times the benefit value of 10.34). That is below 0.06, so buy is still worse under this assumption.