Sub topic 5
Time to Market and the Cost of Delay
Assume you know basic revenue, margin, and cash-flow terms. This chapter also assumes you can compare yearly costs and benefits in a spreadsheet. The key question is simple: how much value is lost while an internal team is still building?
Why speed has economic value
A build option often looks cheaper because its direct spending is spread over several years. That comparison is incomplete. During development, the company may miss sales, lose customers, or allow a competitor to establish a strong position.
The cost of delay is the value the company gives up because a capability is not ready yet. It can include:
- Lost contribution margin from sales that could not be made
- Delayed cost savings
- Customer churn or weaker retention
- A competitor's head start
- Missed learning from launching earlier
- Higher spending needed to catch up later
Use contribution margin rather than revenue when estimating lost sales. Contribution margin is revenue minus the variable costs required to deliver it. It measures the cash contribution that the delayed capability might have produced.
A simple timing model
Suppose an internal build takes three years. It costs $2 million in year 1, $2 million in year 2, and $1 million in year 3. The capability would produce $3 million of annual contribution margin beginning in year 2 if it were available immediately.
The direct build cost is $5 million. However, the company also gives up two years of contribution margin while waiting. At $3 million per year, the undiscounted delay cost is $6 million.
The estimate should reflect when cash flows occur. A benefit in year 4 is worth less today than the same benefit in year 1. Discounting converts future cash flows into present value, which makes timing differences explicit.
| Item | Faster route | Internal build |
|---|---|---|
| Ready for launch | End of year 1 | End of year 3 |
| Direct cost | $10 million | $5 million |
| Contribution margin in year 2 | $3 million | $0 |
| Contribution margin in year 3 | $3 million | $0 |
| Contribution margin in year 4 | $3 million | $3 million |
The faster route may cost more directly but still create more value because it starts producing benefits earlier. Its advantage is largest when margins are high, demand is growing, or the competitive window is short.
Estimating the delay carefully
Do not assume that every delayed sale disappears permanently. Some customers may buy later, and some demand may be uncertain. Separate the estimate into:
- Demand that is likely to exist.
- The share the company could realistically capture.
- Contribution margin per sale.
- The number of months until each route launches.
- The probability that the build meets its schedule.
A useful approximation is:
Delay cost = monthly contribution margin × months delayed × probability of capturing the demand
Run low, base, and high cases. The high case might include a competitor launch or a shorter product life cycle. The base case should use evidence such as customer commitments, sales forecasts, and competitor timelines.
Using timing in the decision
Compare routes using the same time horizon and discount rate. Include direct spending, expected contribution margin, ongoing operating costs, and the cost of delay. Then test whether the result changes when the launch date slips.
If a one-year delay changes the preferred option, schedule confidence becomes a strategic factor. Ask which route has the more credible launch plan, not merely the shorter advertised schedule.
Exercise
A build costs $4 million and takes two years. It would then produce $2 million of annual contribution margin. A purchase costs $8 million and launches after six months. What missing evidence is most important before choosing?
Show answer
Validate the expected demand and margin, then compare the purchase's integration risk and launch timing with the build's schedule risk. The direct prices alone do not capture the value of earlier benefits.